Installation

...

Add The Gadget To Your Dashboard

  1. From within the JIRA dashboard in which you want to add the new gadget, click the Add Gadget button.

  2.  Search for the Filtered Budget Burnup Chart by scrolling through the listed gadgets or filtering via the Search field. 

    Image Modified
  3. Configure your server or cloud gadget.

  4. Once the gadget is configured, click the Save button to display the results in graph.

 

Anchor
Server
Server

Server Plugin Configuration

  1. The server version of the Filtered Budget Burnup Chart gadget has a number of configurable fields to customize the way the gadget displays on your dashboard.

     


  2. The following table shows the gadget configuration options

    ConfigurationDescription
    Project or Saved FilterSelect the project or saved filter that you would like to chart.
    Project or Filter DescriptionAn optional field which allows for a description of the selected project
    /
    or filter.
    Show Remaining EstimateOption to show the remaining estimate (in hours) of all issues of the selected project
    /
    or filter. This is set to Yes by default.
    Trend LineOption to show a trend line based on all work completed. This is set to On by default.
    Set GoalSet a budget of hours which will be displayed as the goal line. If no number is given, a goal line will not appear on chart.
    Start Date / End DateSelect the date range for the data to be displayed.

 



Anchor
Cloud
Cloud
Cloud Plugin Configuration

  1. The  Filtered cloud version of the Filtered Budget Burnup Chart gadget has a number of configurable fields to customize the way the gadget displays on your dashboard.

     


  2. The following table shows the gadget configuration options

    ConfigurationDescription
    Project or Favourite FilterSelect the project or favourite filter that you would like to chart.
    Project or Filter DescriptionAn optional field which allows for a description of the selected project
    /
    or filter.
    Show Remaining EstimateOption to show the remaining estimate (in hours) of all issues of the selected project
    /
    or filter. This is set to Yes by default.
    Trend LineOption to show a trend line based on all work completed. This is set to On by default.
    Set GoalSet a budget of hours which will be displayed as the goal line. If no number is given, a goal line will not appear on chart.
    Start Date / End DateSelect the date range for the data to be displayed.

...